TAP announces progress as of late February

  17 March 2020    Read: 1385
 TAP announces progress as of late February

The progress in the implementation of the Trans Adriatic Pipeline (TAP), the final leg of the Southern Gas Corridor, envisaging transportation of Azerbaijani gas to Europe is 93.5 percent as of late February, Trend reports citing TAP AG consortium.

“TAP is currently moving further into the project construction phase. Every day hundreds of meters of TAP’s Right of Way (ROW) are cleared, strung, welded, lowered into the trenches and backfilled, in line with the project construction steps and schedule.

At the end of February 2020, the TAP project was 93.5 percent completed,” said the consortium.

TAP project, worth 4.5 billion euros, is one of the priority energy projects for the European Union (EU). The project envisages transportation of gas from Azerbaijan's Shah Deniz Stage 2 to the EU countries.

Connecting with the Trans Anatolian Pipeline (TANAP) at the Greek-Turkish border, TAP will cross Northern Greece, Albania and the Adriatic Sea before coming ashore in Southern Italy to connect to the Italian natural gas network.

The project is currently in its construction phase, which started in 2016.

Once built, TAP will offer a direct and cost-effective transportation route opening up the vital Southern Gas Corridor, a 3,500-kilometer long gas value chain stretching from the Caspian Sea to Europe.

TAP shareholders include BP (20 percent), SOCAR (20 percent), Snam S.p.A. (20 percent), Fluxys (19 percent), Enagás (16 percent) and Axpo (5 percent).