BP: Pandemic-related restrictions causes delays on “Azeri Central East” project

  12 May 2020    Read: 1151
BP: Pandemic-related restrictions causes delays on “Azeri Central East” project

During the quarter ACE (Azeri Central East) platform topsides and drilling fabrication activities continued at the Bibi-Heybat fabrication yard. However, the pandemic related restrictions started to cause delays in materials and major equipment deliveries towards the end of the quarter resulting in pauses of activities. The living quarters module fabrication progressed in Sweden, BP Azerbaijan said.

“The jacket fabrication also progressed at the Heydar Aliyev Baku Deepwater Jackets Factory (BDJF). The fabrication of the jacket pin piles is complete for installation later in the year. The subsea fabrication has commenced at BDJF with the subsea pipe coating currently ongoing at Caspian Pipe Coating (CPC),” the company added.

 