He added that the European Investment Bank will allocate $1.3 billion to the Southern Gas Corridor CJSC and BOTAS soon: “Following EBRD’s allocation of $500 million to TANAP, EIB’s this step won’t take long”.
According to him, $3.950 billion in total has been attracted so far: “According to latest calculations, TANAP budget reduced about $7.9 billion. Unlike previous forecast, we invested $3.8 billion in the project. During realization of such project, there are always two goals ahead: time and financial source. We achieved both of these goals”
The General Director noted that more than 13,000 people have been involved in the construction of the project.
Starting June 2018, saleable gas will be transported to Turkey, he added.